Piccadilly IV, Goregaon East

Lapsed

by Royal Palms India Pvt Ltd · Goregaon East, Mumbai 400065 · Map

Launched
Aug 20176 mths originally promised
Possession (MahaRERA)
Feb 2019Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.6 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
42
Total units
42
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 20%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 100%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%–
100%100%20%–
100%100%20%41

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Piccadilly IV by Royal Palms India Pvt Ltd is a 42-unit project in Goregaon East, Mumbai 400065, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Piccadilly IV is a project by Royal Palms India Pvt Ltd in Goregaon East, Mumbai 400065, registered with MahaRERA as P51800004140. It was launched in August 2017. It has 42 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in February 2019, after an extension of 1 year from the original February 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.