- Launched
- Aug 20173 yrs 3 mths originally promised
- Possession (MahaRERA)
- Sep 2023Extended by 2 yrs 10 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 7 of 1839%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 18
- Total units
- 18
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 7 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 7 |
"–" means MahaRERA shows no figure for that update.
About this project
Devdatta Tower by Yashraj Corporation is an 18-unit project in Mulund East, Mumbai 400081, launched in August 2017; its MahaRERA registration has lapsed. 7 units booked out of total 18 units. The concrete structure (RCC) is complete.
Read full summary
Devdatta Tower is a project by Yashraj Corporation in Mulund East, Mumbai 400081, registered with MahaRERA as P51800004163. It was launched in August 2017. It has 18 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in September 2023, after an extension of 2 years 10 months from the original November 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.
7 units booked out of total 18 units (39%).