Devdatta Tower, Mulund East

Lapsed

by Yashraj Corporation · Mulund East, Mumbai 400081 · Map

Launched
Aug 20173 yrs 3 mths originally promised
Possession (MahaRERA)
Sep 2023Extended by 2 yrs 10 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
7 of 1839%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
18
Total units
18
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%7
100%100%0%–
100%100%0%–
100%100%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Devdatta Tower by Yashraj Corporation is an 18-unit project in Mulund East, Mumbai 400081, launched in August 2017; its MahaRERA registration has lapsed. 7 units booked out of total 18 units. The concrete structure (RCC) is complete.

Read full summary

Devdatta Tower is a project by Yashraj Corporation in Mulund East, Mumbai 400081, registered with MahaRERA as P51800004163. It was launched in August 2017. It has 18 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2023, after an extension of 2 years 10 months from the original November 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

7 units booked out of total 18 units (39%).