D N Nagar Niwara Chs Ltd, Andheri West
Lapsed
by Westin Spaces Private Limited · Andheri West, Mumbai 400053 · Map
- Launched
- Aug 20171 yr 7 mths originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 4 yrs 9 mthsWhat does Lapsed mean?
- Concrete structure
- 62%Mid-construction
- Booked
- 14 of 3738%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 15Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 16
- 2 BHK
- 21
- Total units
- 37
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 62% | 0% | 14 | |
| 100% | 62% | 0% | – | |
| 100% | 62% | 0% | – | |
| 100% | 62% | 0% | 14 |
"–" means MahaRERA shows no figure for that update.
About this project
D N Nagar Niwara Chs Ltd by Westin Spaces Private Limited is a 37-unit project in Andheri West, Mumbai 400053, launched in August 2017; its MahaRERA registration has lapsed. 14 units booked out of total 37 units. The concrete structure (RCC) is 62% complete.
Read full summary
D N Nagar Niwara Chs Ltd is a project by Westin Spaces Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800004214. It was launched in August 2017. It has 37 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023, after an extension of 4 years 9 months from the original March 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 62% complete, final finishes not started.
14 units booked out of total 37 units (38%).