Skip to main content

Building No 3 Wing A Epsilon, Kandivali East

Lapsed

by SD Corporation Private Limited · Kandivali East, Mumbai 400101 · Map

Launched
Aug 20174 yrs 7 mths promised
Possession (MahaRERA)
Mar 2022Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.9 acres
MahaRERA complaints
11Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
158
3 BHK
74
Total units
232
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%–
100%100%60%–
100%100%60%232

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Building No 3 Wing A Epsilon by SD Corporation Private Limited is a 232-unit project in Kandivali East, Mumbai 400101, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Building No 3 Wing A Epsilon is a project by SD Corporation Private Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800004355. It was launched in August 2017. It has 232 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2022. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.