Premier Exotica, Kurla West
Lapsed
by Housing Development And Infrastructure Ltd · Kurla West, Mumbai 400070 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2019 – Jan 2021Extended in 1 of 2 phasesWhat does Lapsed mean?
- Concrete structure
- 85%Weighted across 2 phases
- Booked
- –
- Buildings
- 72.2 acres
- MahaRERA complaints
- 12Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 602
- Total units
- 602
- Buildings
- 7
- Land
- 2.2 acres
- Phases
- 2
- MahaRERA complaints
- 12
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Premier Exotica I Mid-construction Lapsed | P51800004431 | 0 | 83% | 93% | |
| Premier Exotica II Ready to move Lapsed | P51800016598 | 0 | 100% | – |
Show updates by phase
Premier Exotica I (P51800004431)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 83% | 83% | 30% | 482 | |
| 83% | 83% | 30% | – | |
| 83% | 83% | 30% | – | |
| 83% | 83% | 30% | 482 |
"–" means MahaRERA shows no figure for that update.
Premier Exotica II (P51800016598)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Premier Exotica by Housing Development And Infrastructure Ltd is a 602-unit project in Kurla West, Mumbai 400070, registered with MahaRERA in 2 phases, with possession dates from December 2019 to January 2021. The concrete structure (RCC) is 85% complete.
Read full summary
Premier Exotica is a project by Housing Development And Infrastructure Ltd in Kurla West, Mumbai 400070, registered with MahaRERA as 2 phases (P51800004431, P51800016598). The first phase was launched in August 2017. Together the phases have 602 units in 7 buildings, as registered with MahaRERA. Both phases are lapsed on MahaRERA.
The phases' registered possession dates run from December 2019 to January 2021; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 85% complete and final finishes 38% complete. Neither phase has its structure complete.