Krishna Kamal, Borivali East
Lapsed
by Graphic Housing Developments Pvt Ltd · Borivali East, Mumbai 400066 · Map
- Launched
- Aug 20172 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2024Extended by 4 yrs 9 mthsWhat does Lapsed mean?
- Concrete structure
- 40%Mid-construction
- Booked
- 1 of 1100%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 1
- Total units
- 1
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 40% | 0% | 1 | |
| 100% | 40% | 0% | 1 | |
| 100% | 40% | 0% | 1 | |
| 100% | 40% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
About this project
Krishna Kamal by Graphic Housing Developments Pvt Ltd is a 1-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in August 2017; its MahaRERA registration has lapsed. 1 unit booked out of total 1 unit. The concrete structure (RCC) is 40% complete.
Read full summary
Krishna Kamal is a BMC-sanctioned project by Graphic Housing Developments Pvt Ltd in Borivali East, Mumbai 400066, registered with MahaRERA as P51800004484. It was launched in August 2017. It has 1 unit in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024, after an extension of 4 years 9 months from the original March 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.
1 unit booked out of total 1 unit (100%).