Skip to main content

to E on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheri, Santacruz East

Lapsed

by A A Estates Pvt Ltd · Santacruz East, Mumbai 400098 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Aug 2023Not extendedWhat does Lapsed mean?
Concrete structure
5%Weighted across 2 phases
Booked
177 of 50935%
Buildings
51.7 acres
MahaRERA complaints
10Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
243
3 BHK
247
4 BHK
18
Total units
509
Buildings
5
Land
1.7 acres
Phases
2
MahaRERA complaints
10

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Tower A to E on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheri
Mid-construction Lapsed
P518000046433827%46%
Tower F and G on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheri
Early stage Lapsed
P518000049181270%1%
Show updates by phase

Tower A to E on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheri (P51800004643)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%7%0%176
100%7%0%–
100%7%0%–
100%7%0%176

"–" means MahaRERA shows no figure for that update.

Tower F and G on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheri (P51800004918)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
25%0%0%1
25%0%0%–
25%0%0%–
25%0%0%1

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation81%
Concrete structure (slabs)5%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 81%Dec 2025: Excavation 81%Jul 2026: Excavation 81%Oct 2026: Excavation 81%Dec 2024: Concrete structure (RCC) 5%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 5%Oct 2026: Concrete structure (RCC) 5%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 81%Concrete structure (RCC) 5%Final finishes 0%

How to read construction stages

About this project

to E on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheri by A A Estates Pvt Ltd is a 509-unit project in Santacruz East, Mumbai 400098, registered with MahaRERA in 2 phases, with possession due in August 2023. 177 units booked out of total 509 units. The concrete structure (RCC) is 5% complete.

Read full summary

to E on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheri is a project by A A Estates Pvt Ltd in Santacruz East, Mumbai 400098, registered with MahaRERA as 2 phases (P51800004643, P51800004918). The first phase was launched in August 2017. Together the phases have 509 units in 5 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Both phases are lapsed on MahaRERA.

The registered possession date is August 2023; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 5% complete and final finishes 0% complete. Neither phase has its structure complete.

177 units booked out of total 509 units (35%).