Shashikala Premises Co-Operative Society Limited, Goregaon East

Lapsed

by Heartland Habitats LLP · Goregaon East, Mumbai 400063 · Map

Launched
Aug 20171 yr 11 mths originally promised
Possession (MahaRERA)
Jul 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%–
100%100%0%–
100%100%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shashikala Premises Co-Operative Society Limited by Heartland Habitats LLP is a project in Goregaon East, Mumbai 400063, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Shashikala Premises Co-Operative Society Limited is a project by Heartland Habitats LLP in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800004683. It was launched in August 2017. Its MahaRERA status is Lapsed.

Possession was due in July 2020, after an extension of 1 year from the original July 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.