Aditya Enterprises, Borivali West

Lapsed

by Aditya Enterprise · Borivali West, Mumbai 400103 · Map

Launched
Aug 20173 yrs 10 mths promised
Possession (MahaRERA)
Jun 2021Not extendedWhat does Lapsed mean?
Concrete structure
67%Mid-construction
Booked
–
Buildings
20.7 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
2
2 BHK
107
3 BHK
14
Other units
23
Total units
146
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation67%
Concrete structure (slabs)67%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 67%Jul 2026: Excavation 67%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 67%Dec 2024: Final finishes 75%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 67%Concrete structure (RCC) 67%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%67%50%–
67%67%50%–
100%100%75%96

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Aditya Enterprises by Aditya Enterprise is a 146-unit project in Borivali West, Mumbai 400103, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 67% complete.

Read full summary

Aditya Enterprises is a project by Aditya Enterprise in Borivali West, Mumbai 400103, registered with MahaRERA as P51800004821. It was launched in August 2017. It has 146 units in 2 buildings: 123 homes (1, 2 and 3 BHK) and 23 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2021. That date has passed and no extension has been recorded. Construction: excavation 67% complete, structure (RCC) 67% complete, final finishes 50% complete.