Ten Bkc, Bandra East
Lapsed
by MIG (Bandra) Realtors & Builders Private Limited · Bandra East, Mumbai 400051 · Map
- Launched
- Aug 20175 yrs 10 mths originally promised
- Possession (MahaRERA)
- Jun 2025Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 155 acres
- MahaRERA complaints
- 82Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 1
- Total units
- 1
- Buildings
- 15
- Land
- 5 acres
- Phases
- 1
- MahaRERA complaints
- 82
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 46% | 479 | |
| 100% | 100% | 46% | 0 | |
| 100% | 100% | 46% | 0 | |
| 100% | 100% | 46% | 479 |
"–" means MahaRERA shows no figure for that update.
About this project
Ten Bkc by MIG (Bandra) Realtors & Builders Private Limited is a 1-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Ten Bkc is a MHADA-sanctioned project by MIG (Bandra) Realtors & Builders Private Limited in Bandra East, Mumbai 400051, registered with MahaRERA as P51800004889. It was launched in August 2017. It has 1 unit in 15 buildings, with 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025, after an extension of 2 years from the original June 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 46% complete.