Parijat Height, Kandivali East

Lapsed

by Mohammed Ismail Zahiruddin Shaikh · Kandivali East, Mumbai 400101 · Map

Launched
Aug 20173 yrs 5 mths promised
Possession (MahaRERA)
Jan 2021Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
32
Total units
32
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation70%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 70%Dec 2025: Excavation 70%Jul 2026: Excavation 70%Oct 2026: Excavation 70%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 70%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%0%0%–
70%0%0%–
70%0%0%–
70%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Parijat Height by Mohammed Ismail Zahiruddin Shaikh is a 32-unit project in Kandivali East, Mumbai 400101, launched in August 2017; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Parijat Height is a project by Mohammed Ismail Zahiruddin Shaikh in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800005096. It was launched in August 2017. It has 32 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2021. That date has passed and no extension has been recorded. Construction: excavation 70% complete, structure (RCC) not started, final finishes not started.