C And J Corporate Park, Chandivali

Lapsed

by Anil Arora · Chandivali, Mumbai 400072 · Map

Launched
Aug 20172 yrs 8 mths originally promised
Possession (MahaRERA)
Apr 2022Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
168 of 19984%
Buildings
11.9 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
199
Total units
199
Buildings
1
Land
1.9 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%168
100%100%60%–
100%100%60%–
100%100%60%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

C And J Corporate Park by Anil Arora is a 199-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in August 2017; its MahaRERA registration has lapsed. 168 units booked out of total 199 units. The concrete structure (RCC) is complete.

Read full summary

C And J Corporate Park is a BMC-sanctioned project by Anil Arora in Chandivali, Mumbai 400072, registered with MahaRERA as P51800005593. It was launched in August 2017. It has 199 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in April 2022, after an extension of 2 years from the original April 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

168 units booked out of total 199 units (84%). Since the July 2026 update, the possession date has moved from April 2020 to April 2022.