- Launched
- Aug 20172 yrs 8 mths originally promised
- Possession (MahaRERA)
- Apr 2022Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 168 of 19984%
- Buildings
- 11.9 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 199
- Total units
- 199
- Buildings
- 1
- Land
- 1.9 acres
- Phases
- 1
- MahaRERA complaints
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 168 | |
| 100% | 100% | 60% | – | |
| 100% | 100% | 60% | – | |
| 100% | 100% | 60% | 2 |
"–" means MahaRERA shows no figure for that update.
About this project
C And J Corporate Park by Anil Arora is a 199-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in August 2017; its MahaRERA registration has lapsed. 168 units booked out of total 199 units. The concrete structure (RCC) is complete.
Read full summary
C And J Corporate Park is a BMC-sanctioned project by Anil Arora in Chandivali, Mumbai 400072, registered with MahaRERA as P51800005593. It was launched in August 2017. It has 199 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in April 2022, after an extension of 2 years from the original April 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.
168 units booked out of total 199 units (84%). Since the July 2026 update, the possession date has moved from April 2020 to April 2022.