Heritage, Chandivali

Lapsed

by Crystal Developers · Chandivali, Mumbai 400072 · Map

Launched
Aug 20175 yrs 4 mths promised
Possession (MahaRERA)
Dec 2022Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
1
2 BHK
36
4 BHK
3
Other units
9
Total units
50
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Heritage by Crystal Developers is a 50-unit project in Chandivali, Mumbai 400072, launched in August 2017; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Heritage is a project by Crystal Developers in Chandivali, Mumbai 400072, registered with MahaRERA as P51800005701. It was launched in August 2017. It has 50 units in 1 building: 41 homes (1 RK, 1 BHK, 2 BHK and 4 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2022. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.