Celestial Heights, Malad West

by Ayyappa Developers Pvt Ltd · Malad West, Mumbai 400064 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Dec 2029Extended in 1 of 2 phases
Concrete structure
22%Weighted across 2 phases
Booked
–
Buildings
20.6 acres
MahaRERA complaints
13Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
10
5+ BHK
1
Other units
76
Total units
87
Buildings
2
Land
0.6 acres
Phases
2
MahaRERA complaints
13

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Celestial Heights
Completed
P518000058120––
Celestial Heights - Phase II
Early stage
P51800079791110%0%
Show updates by phase

Celestial Heights (P51800005812)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%–
100%25%0%–
100%25%0%34

"–" means MahaRERA shows no figure for that update.

Celestial Heights - Phase II (P51800079791)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)22%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 87%Jul 2026: Excavation 87%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 22%Jul 2026: Concrete structure (RCC) 22%Oct 2026: Concrete structure (RCC) 22%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 22%Final finishes 0%

How to read construction stages

Compared with 4 similar projects in PIN 400064

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 1 mth1 yr 5 mths
Possession date extendedYes4 of 4
Possession date (MahaRERA)Dec 2029Nov 2025
Concrete structure (RCC)22%56%
Units booked–81%
MahaRERA complaints (filed by or against the builder)132

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Celestial Heights by Ayyappa Developers Pvt Ltd is an 87-unit SRA-sanctioned project in Malad West, Mumbai 400064, registered with MahaRERA in 2 phases, with possession due in December 2029. The concrete structure (RCC) is 22% complete.

Read full summary

Celestial Heights is an SRA-sanctioned project by Ayyappa Developers Pvt Ltd in Malad West, Mumbai 400064, registered with MahaRERA as 2 phases (P51800005812, P51800079791). The first phase was launched in August 2017. Together the phases have 87 units in 2 buildings: 11 homes (4 and 5+ BHK) and 76 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is December 2029; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 22% complete and final finishes 0% complete. Neither phase has its structure complete.