New Simit Apartment, Malad West

Lapsed

by Reliable Buildhights LLP · Malad West, Mumbai 400064 · Map

Launched
Aug 20172 yrs 2 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 5 yrs 2 mthsWhat does Lapsed mean?
Concrete structure
50%Mid-construction
Booked
15 of 1883%
Buildings
10.1 acres
MahaRERA complaints
11Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
6
2 BHK
7
3 BHK
4
Total units
18
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 20%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 50%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%20%15
100%50%20%–
100%50%20%–
100%50%20%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400064

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 2 mths1 yr 5 mths
Possession date extendedBy 5 yrs 2 mths5 of 5
Possession date (MahaRERA)Dec 2024Oct 2026
Concrete structure (RCC)50%63%
Units booked83%62%
MahaRERA complaints (filed by or against the builder)114

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

New Simit Apartment by Reliable Buildhights LLP is an 18-unit project in Malad West, Mumbai 400064, launched in August 2017; its MahaRERA registration has lapsed. 15 units booked out of total 18 units. The concrete structure (RCC) is 50% complete.

Read full summary

New Simit Apartment is a project by Reliable Buildhights LLP in Malad West, Mumbai 400064, registered with MahaRERA as P51800010193. It was launched in August 2017. It has 18 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 5 years 2 months from the original October 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 50% complete, final finishes 20% complete.

15 units booked out of total 18 units (83%).