Delphine Chsl, Kandivali West
by Glasswood Realty Private Limited · Kandivali West, Mumbai 400067 · Map
- Launched
- Aug 20173 yrs 1 mth originally promised
- Possession (MahaRERA)
- Oct 2028Extended by 8 yrs 1 mth
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 4 of 850% · 33 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 8 units
Rehab33 units for existing members
Total 41 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 18
- 2 BHK
- 15
- 3 BHK
- 2
- Other units
- 6
- Total units
- 41
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 8
- Rehab units
- 33
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 4 | |
| 100% | 100% | 0% | 4 | |
| 100% | 59% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 1 mth | 2 yrs 3 mths |
| Possession date extended | By 8 yrs 1 mth | 6 of 6 |
| Possession date (MahaRERA) | Oct 2028 | Sep 2024 |
| Concrete structure (RCC) | 100% | 78% |
| Units booked (free sale) | 50% | 61% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 6 projects
- Kandivali Geeta Sadan Chs Ltd, Kandivali West
- Kavya Kcd Prestine, Kandivali West
- Kandivali Satyam Apartment Chs Ltd, Kandivali West
- Vision Heeraji, Kandivali West
- Arpan Chs Ltd, Kandivali West
- Rite Perinto, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kandivali Geeta Sadan Chs Ltd | August 2017 | April 2025 | 95% | 22 units booked out of 23 units for sale |
| Kavya Kcd Prestine | August 2017 | September 2028 | 64% | 3 units booked out of 18 units for sale |
| Kandivali Satyam Apartment Chs Ltd | August 2017 | December 2024 | 92% | 19 units booked out of total 31 units |
| Vision Heeraji | August 2017 | December 2022 | 40% | 16 units booked out of total 34 units |
| Arpan Chs Ltd | August 2017 | June 2024 | 11% | 26 units booked out of total 26 units |
| Rite Perinto | August 2017 | March 2022 | 100% | – |
About this project
Delphine Chsl by Glasswood Realty Private Limited is a 41-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in August 2017 with possession due in October 2028. 4 units booked out of 8 units for sale. The concrete structure (RCC) is complete.
Read full summary
Delphine Chsl is a BMC-sanctioned project by Glasswood Realty Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800005847. It was launched in August 2017. It has 41 units in 1 building: 35 homes (1, 2 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 41 units, 8 are for sale and 33 are rehab units for existing members.
Its registered possession date is October 2028, extended by 8 years 1 month from the original September 2020. Construction: excavation complete, structure (RCC) complete, final finishes not started.
4 units booked out of 8 units for sale (50%).