Kandivali Geeta Sadan Chs Ltd, Kandivali West

Lapsed

by Ms Prathmesh Landmark Consultancy · Kandivali West, Mumbai 400067 · Map

Launched
Aug 20171 yr 10 mths originally promised
Possession (MahaRERA)
Apr 2025Extended by 5 yrs 10 mthsWhat does Lapsed mean?
Concrete structure
95%Mid-construction
Booked (free sale)
22 of 2396% · 22 rehab units
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale22 booked out of 23 units

Rehab22 units for existing members

Total 45 units. Rehab units are not for sale.

Project facts

2 BHK
26
3 BHK
10
Other units
9
Total units
45
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
23
Rehab units
22

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 95%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%0%22
100%95%0%22
100%95%0%22
100%90%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 10 mths2 yrs 10 mths
Possession date extendedBy 5 yrs 10 mths6 of 6
Possession date (MahaRERA)Apr 2025Jun 2025
Concrete structure (RCC)95%94%
Units booked (free sale)96%60%
MahaRERA complaints (filed by or against the builder)12

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Kandivali Geeta Sadan Chs Ltd by Ms Prathmesh Landmark Consultancy is a 45-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in August 2017; its MahaRERA registration has lapsed. 22 units booked out of 23 units for sale. The concrete structure (RCC) is 95% complete.

Read full summary

Kandivali Geeta Sadan Chs Ltd is a BMC-sanctioned project by Ms Prathmesh Landmark Consultancy in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800006861. It was launched in August 2017. It has 45 units in 1 building: 36 homes (2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 45 units, 23 are for sale and 22 are rehab units for existing members.

Possession was due in April 2025, after an extension of 5 years 10 months from the original June 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.

22 units booked out of 23 units for sale (96%).