The Elite, Mulund West
by R R D Heights And Builders Pvt Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 95%Mid-construction
- Booked
- 211 of 21598% · 209 in Jul 2026
- Buildings
- 21.8 acres
- MahaRERA complaints
- 14Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 112
- 3 BHK
- 81
- 4 BHK
- 1
- 5+ BHK
- 16
- Other units
- 5
- Total units
- 215
- Buildings
- 2
- Land
- 1.8 acres
- Phases
- 1
- MahaRERA complaints
- 14
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 80% | 95% | 10% | 211 | |
| 80% | 94% | 7% | 209 | |
| 80% | 94% | 7% | – | |
| 80% | 93% | 4% | 207 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 5 yrs 1 mth |
| Possession date extended | By 3 yrs 4 mths | 6 of 6 |
| Possession date (MahaRERA) | Apr 2027 | Jun 2025 |
| Concrete structure (RCC) | 95% | 100% |
| Units booked | 98% | 79% |
| MahaRERA complaints (filed by or against the builder) | 14 | 6 |
The 6 projects
- Keshavpada, Mulund West
- Ashoka Heights, Mulund West
- Morphosis Adagio, Mulund West
- Sunshine Tower Phase - I, Mulund West
- Raj Altezza, Mulund West
- Silver Park, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Keshavpada | August 2017 | December 2028 | 100% | 151 units booked out of total 207 units |
| Ashoka Heights | August 2017 | December 2025 | 100% | 190 units booked out of total 222 units |
| Morphosis Adagio | August 2017 | December 2024 | 100% | – |
| Sunshine Tower Phase - I | August 2017 | December 2026 | 65% | 150 units booked out of 155 units for sale |
| Raj Altezza | August 2017 | July 2024 | 83% | 110 units booked out of total 150 units |
| Silver Park | August 2017 | April 2020 | 100% | – |
About this project
The Elite by R R D Heights And Builders Pvt Ltd is a 215-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017 with possession due in April 2027. 211 units booked out of total 215 units. The concrete structure (RCC) is 95% complete.
Read full summary
The Elite is an SRA-sanctioned project by R R D Heights And Builders Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800005901. It was launched in August 2017. It has 215 units in 2 buildings: 210 homes (2, 3, 4 and 5+ BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation 80% complete, structure (RCC) 95% complete, final finishes 10% complete.
211 units booked out of total 215 units (98%). Since the July 2026 update, 2 more units have been booked, the reported concrete structure (RCC) has gone from 94% to 95% and the possession date has moved from December 2024 to April 2027.