Raj Altezza, Mulund West
Lapsed
by Rajguru Developers Private Limited · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 20172 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jul 2024Extended by 4 yrs 7 mthsWhat does Lapsed mean?
- Concrete structure
- 83%Mid-construction
- Booked
- 110 of 15073%
- Buildings
- 10.7 acres
- MahaRERA complaints
- 13Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 100
- 3 BHK
- 50
- Total units
- 150
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 83% | 2% | 110 | |
| 100% | 83% | 2% | – | |
| 100% | 83% | 2% | – | |
| 100% | 83% | 2% | 110 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 4 mths | 6 yrs 4 mths |
| Possession date extended | By 4 yrs 7 mths | 6 of 6 |
| Possession date (MahaRERA) | Jul 2024 | Feb 2027 |
| Concrete structure (RCC) | 83% | 98% |
| Units booked | 73% | 92% |
| MahaRERA complaints (filed by or against the builder) | 13 | 4 |
The 6 projects
- Silver Park, Mulund West
- Sunshine Tower Phase - I, Mulund West
- Marigold Miraaya, Mulund West
- Arihant Royale, Mulund West
- Keshavpada, Mulund West
- The Elite, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Silver Park | August 2017 | April 2020 | 100% | – |
| Sunshine Tower Phase - I | August 2017 | December 2026 | 65% | 150 units booked out of 155 units for sale |
| Marigold Miraaya | August 2017 | June 2025 | 100% | 50 units booked out of total 133 units |
| Arihant Royale | August 2017 | April 2027 | 62% | 142 units booked out of total 154 units |
| Keshavpada | August 2017 | December 2028 | 100% | 151 units booked out of total 207 units |
| The Elite | August 2017 | April 2027 | 95% | 211 units booked out of total 215 units |
About this project
Raj Altezza by Rajguru Developers Private Limited is a 150-unit project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 110 units booked out of total 150 units. The concrete structure (RCC) is 83% complete.
Read full summary
Raj Altezza is a project by Rajguru Developers Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800007125. It was launched in August 2017. It has 150 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in July 2024, after an extension of 4 years 7 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 83% complete, final finishes 2% complete.
110 units booked out of total 150 units (73%).