Rishabh Tower, Andheri West

Lapsed

by Vipul Pravinchandra Shah · Andheri West, Mumbai 400053 · Map

Launched
Aug 201710 mths originally promised
Possession (MahaRERA)
Jun 2020Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
90%Mid-construction
Booked
–
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
52
Total units
52
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)90%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Excavation 95%Concrete structure (RCC) 90%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%90%80%–
95%90%80%–
95%90%80%17

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Rishabh Tower by Vipul Pravinchandra Shah is a 52-unit project in Andheri West, Mumbai 400053, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 90% complete.

Read full summary

Rishabh Tower is a project by Vipul Pravinchandra Shah in Andheri West, Mumbai 400053, registered with MahaRERA as P51800006332. It was launched in August 2017. It has 52 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2020, after an extension of 2 years from the original June 2018. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 90% complete, final finishes 80% complete.