Shreedham Splendour, Andheri West

Lapsed

by Shreedham Builders · Andheri West, Mumbai 400053 · Map

Launched
Aug 20171 yr 10 mths originally promised
Possession (MahaRERA)
Jun 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
90%Mid-construction
Booked
–
Buildings
10.8 acres
MahaRERA complaints
5Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
Other units
117
Total units
118
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation97%
Concrete structure (slabs)90%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 97%Dec 2025: Excavation 97%Jul 2026: Excavation 97%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 30%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Excavation 97%Concrete structure (RCC) 90%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
97%90%30%–
97%90%30%–
97%90%30%111

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shreedham Splendour by Shreedham Builders is a 118-unit project in Andheri West, Mumbai 400053, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 90% complete.

Read full summary

Shreedham Splendour is a project by Shreedham Builders in Andheri West, Mumbai 400053, registered with MahaRERA as P51800006344. It was launched in August 2017. It has 118 units in 1 building: 1 home (1 BHK) and 117 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2020, after an extension of 1 year from the original June 2019. That date has passed and no further extension has been recorded. Construction: excavation 97% complete, structure (RCC) 90% complete, final finishes 30% complete.