Nirmal Lifestyle-Discovery, Mulund West

Lapsed

by Nirmal Lifestyle Ltd · Mulund West, Mumbai 400080 · Map

Launched
Aug 20176 yrs 4 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
17%Mid-construction
Booked
193 of 68028%
Buildings
10.4 acres
MahaRERA complaints
19Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
680
Total units
680
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)17%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 17%Dec 2025: Concrete structure (RCC) 17%Jul 2026: Concrete structure (RCC) 17%Oct 2026: Concrete structure (RCC) 17%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 17%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%17%0%193
100%17%0%–
100%17%0%–
100%17%0%193

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nirmal Lifestyle-Discovery by Nirmal Lifestyle Ltd is a 680-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 193 units booked out of total 680 units. The concrete structure (RCC) is 17% complete.

Read full summary

Nirmal Lifestyle-Discovery is a BMC-sanctioned project by Nirmal Lifestyle Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800006781. It was launched in August 2017. It has 680 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 17% complete, final finishes not started.

193 units booked out of total 680 units (28%).