Neelkanthdhara, Ghatkopar West

Lapsed

by Ashapura Developers · Ghatkopar West, Mumbai 400086 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 4 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
97%Mid-construction
Booked
–
Buildings
10.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
Total units
1
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)97%
Finishes, lifts and services97%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 97%Dec 2025: Concrete structure (RCC) 97%Jul 2026: Concrete structure (RCC) 97%Oct 2026: Concrete structure (RCC) 97%Dec 2024: Final finishes 97%Dec 2025: Final finishes 97%Jul 2026: Final finishes 97%Oct 2026: Final finishes 97%Excavation 100%Concrete structure (RCC) 97%Final finishes 97%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%97%104
100%97%97%–
100%97%97%–
100%97%97%104

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Neelkanthdhara by Ashapura Developers is a 1-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 97% complete.

Read full summary

Neelkanthdhara is a BMC-sanctioned project by Ashapura Developers in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800007105. It was launched in August 2017. It has 1 unit in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 4 years 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 97% complete, final finishes 97% complete.

Since the July 2026 update, the possession date has moved from June 2022 to December 2025.