- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 4 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 97%Mid-construction
- Booked
- –
- Buildings
- 10.6 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- Total units
- 1
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 97% | 104 | |
| 100% | 97% | 97% | – | |
| 100% | 97% | 97% | – | |
| 100% | 97% | 97% | 104 |
"–" means MahaRERA shows no figure for that update.
About this project
Neelkanthdhara by Ashapura Developers is a 1-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 97% complete.
Read full summary
Neelkanthdhara is a BMC-sanctioned project by Ashapura Developers in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800007105. It was launched in August 2017. It has 1 unit in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025, after an extension of 4 years 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 97% complete, final finishes 97% complete.
Since the July 2026 update, the possession date has moved from June 2022 to December 2025.