Lapsed

by Man Infraprojects Limited · Vile Parle West, Mumbai 400056 · Map

Launched
Aug 20173 yrs 6 mths promised
Possession (MahaRERA)
Feb 2021Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
22 of 2976%
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
29
Total units
29
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%22
100%100%80%–
100%100%80%–
100%100%80%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Man Excellenza by Man Infraprojects Limited is a 29-unit project in Vile Parle West, Mumbai 400056, launched in August 2017; its MahaRERA registration has lapsed. 22 units booked out of total 29 units. The concrete structure (RCC) is complete.

Read full summary

Man Excellenza is a project by Man Infraprojects Limited in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800007139. It was launched in August 2017. It has 29 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in February 2021. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

22 units booked out of total 29 units (76%).