Vidhya Darshan, Vikhroli

Lapsed

by Aditya Enterprises · Vikhroli, Mumbai 400083 · Map

Launched
Aug 20172 yrs originally promised
Possession (MahaRERA)
Aug 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
66%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
31
2 BHK
47
Other units
9
Total units
87
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)66%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 66%Dec 2025: Concrete structure (RCC) 66%Jul 2026: Concrete structure (RCC) 66%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 66%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%66%60%–
100%66%60%–
100%66%60%77

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vidhya Darshan by Aditya Enterprises is an 87-unit project in Vikhroli, Mumbai 400083, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 66% complete.

Read full summary

Vidhya Darshan is a project by Aditya Enterprises in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800007194. It was launched in August 2017. It has 87 units in 1 building: 78 homes (1 and 2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in August 2020, after an extension of 1 year from the original August 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 66% complete, final finishes 60% complete.