Lapsed

by Damodar Suruchi Developers Pvt Ltd · Kandivali East, Mumbai 400101 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Oct 2024Extended by 10 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
23.3 acres
MahaRERA complaints
44Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
325
2 BHK
173
Other units
20
Total units
518
Buildings
2
Land
3.3 acres
Phases
1
MahaRERA complaints
44

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%–
100%100%80%–
100%100%80%471

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

UK Iridium by Damodar Suruchi Developers Pvt Ltd is a 518-unit project in Kandivali East, Mumbai 400101, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

UK Iridium is a project by Damodar Suruchi Developers Pvt Ltd in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800007275. It was launched in August 2017. It has 518 units in 2 buildings: 498 homes (1 and 2 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2024, after an extension of 10 months from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.