Majestic Towers, Bhandup West
Lapsed
by Housing Development And Infrastructure Ltd · Bhandup West, Mumbai 400078 · Map
- Launched
- Aug 20173 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2020Not extendedWhat does Lapsed mean?
- Concrete structure
- 31%Mid-construction
- Booked
- 401 of 96442%
- Buildings
- 72.4 acres
- MahaRERA complaints
- 120Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 340
- 3 BHK
- 558
- Other units
- 66
- Total units
- 964
- Buildings
- 7
- Land
- 2.4 acres
- Phases
- 1
- MahaRERA complaints
- 120
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 57% | 31% | 0% | 401 | |
| 57% | 31% | 0% | – | |
| 57% | 31% | 0% | – | |
| 57% | 31% | 0% | 401 |
"–" means MahaRERA shows no figure for that update.
About this project
Majestic Towers by Housing Development And Infrastructure Ltd is a 964-unit project in Bhandup West, Mumbai 400078, launched in August 2017; its MahaRERA registration has lapsed. 401 units booked out of total 964 units. The concrete structure (RCC) is 31% complete.
Read full summary
Majestic Towers is a project by Housing Development And Infrastructure Ltd in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800007283. It was launched in August 2017. It has 964 units in 7 buildings: 898 homes (2 and 3 BHK) and 66 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2020. That date has passed and no extension has been recorded. Construction: excavation 57% complete, structure (RCC) 31% complete, final finishes not started.
401 units booked out of total 964 units (42%).