Infina Gardens, Ghatkopar East

Lapsed

by Infina Ashapura Homes LLP · Ghatkopar East, Mumbai 400075 · Map

Launched
Aug 20173 yrs 3 mths originally promised
Possession (MahaRERA)
Nov 2021Extended by 1 yrWhat does Lapsed mean?
Concrete structure
67%Mid-construction
Booked
1 of 617%
Buildings
30.8 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
6
Total units
6
Buildings
3
Land
0.8 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)67%
Finishes, lifts and services67%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 67%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 67%Dec 2024: Final finishes 67%Dec 2025: Final finishes 67%Jul 2026: Final finishes 67%Excavation 100%Concrete structure (RCC) 67%Final finishes 67%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%67%1
100%67%67%–
100%67%67%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Infina Gardens by Infina Ashapura Homes LLP is a 6-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400075, launched in August 2017; its MahaRERA registration has lapsed. 1 unit booked out of total 6 units. The concrete structure (RCC) is 67% complete.

Read full summary

Infina Gardens is a BMC-sanctioned project by Infina Ashapura Homes LLP in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800007427. It was launched in August 2017. It has 6 units in 3 buildings, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in November 2021, after an extension of 1 year from the original November 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 67% complete, final finishes 67% complete.

1 unit booked out of total 6 units (17%).