Satguru CHS Ltd, Kandivali West
Lapsed
by Sai Tasveer Developers · Kandivali West, Mumbai 400067 · Map
- Launched
- Aug 201710 mths originally promised
- Possession (MahaRERA)
- Jun 2020Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 20.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 13
- 2 BHK
- 12
- Total units
- 25
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | – | |
| 100% | 100% | 65% | – | |
| 100% | 100% | 65% | 22 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 10 mths | 3 yrs |
| Possession date extended | By 2 yrs | 6 of 6 |
| Possession date (MahaRERA) | Jun 2020 | Sep 2023 |
| Concrete structure (RCC) | 100% | 91% |
| Units booked | – | 78% |
| MahaRERA complaints (filed by or against the builder) | 1 | 1 |
The 6 projects
- Arpan Chs Ltd, Kandivali West
- Vision Heeraji, Kandivali West
- Kandivali Satyam Apartment Chs Ltd, Kandivali West
- Shree Prafull CHSL, Kandivali West
- Rite Perinto, Kandivali West
- Kavya Shree Laxmi, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Arpan Chs Ltd | August 2017 | June 2024 | 11% | 26 units booked out of total 26 units |
| Vision Heeraji | August 2017 | December 2022 | 40% | 16 units booked out of total 34 units |
| Kandivali Satyam Apartment Chs Ltd | August 2017 | December 2024 | 92% | 19 units booked out of total 31 units |
| Shree Prafull CHSL | August 2017 | March 2022 | 100% | – |
| Rite Perinto | August 2017 | March 2022 | 100% | – |
| Kavya Shree Laxmi | August 2017 | December 2025 | 90% | 19 units booked out of total 20 units |
About this project
Satguru CHS Ltd by Sai Tasveer Developers is a 25-unit project in Kandivali West, Mumbai 400067, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Satguru CHS Ltd is a project by Sai Tasveer Developers in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800007430. It was launched in August 2017. It has 25 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2020, after an extension of 2 years from the original June 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 65% complete.