Ariisto Sommet-Retail, Goregaon West
Lapsed
by Atithi Builders And Constructors Private Limited · Goregaon West, Mumbai 400090 · Map
- Launched
- Aug 20176 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2023Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 12.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 22
- Total units
- 22
- Buildings
- 1
- Land
- 2.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Ariisto Sommet-Retail by Atithi Builders And Constructors Private Limited is a 22-unit project in Goregaon West, Mumbai 400090, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Ariisto Sommet-Retail is a project by Atithi Builders And Constructors Private Limited in Goregaon West, Mumbai 400090, registered with MahaRERA as P51800007616. It was launched in August 2017. It has 22 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.