- Launched
- Aug 20171 yr 1 mth originally promised
- Possession (MahaRERA)
- Mar 2022Extended by 3 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 60%Mid-construction
- Booked
- 6 of 1060%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 8
- 5+ BHK
- 2
- Total units
- 10
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 60% | 6 | |
| 100% | 60% | 60% | – | |
| 100% | 60% | 60% | – | |
| 100% | 60% | 60% | 6 |
"–" means MahaRERA shows no figure for that update.
About this project
Kamla Heritage by Kamla Landmarc Builders is a 10-unit project in Juhu, Mumbai 400049, launched in August 2017; its MahaRERA registration has lapsed. 6 units booked out of total 10 units. The concrete structure (RCC) is 60% complete.
Read full summary
Kamla Heritage is a project by Kamla Landmarc Builders in Juhu, Mumbai 400049, registered with MahaRERA as P51800007924. It was launched in August 2017. It has 10 units in 1 building, with 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2022, after an extension of 3 years 6 months from the original September 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 60% complete, final finishes 60% complete.
6 units booked out of total 10 units (60%).