Sea Breeze CHS Ltd, Chembur
Lapsed
by NDZ Infrastructure Private Limited · Chembur, Mumbai 400074 · Map
- Launched
- Aug 20175 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2022Not extendedWhat does Lapsed mean?
- Concrete structure
- 38%Mid-construction
- Booked
- 120 of 23950%
- Buildings
- 41.2 acres
- MahaRERA complaints
- 18Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 16
- 1 BHK
- 159
- 2 BHK
- 55
- 3 BHK
- 8
- 4 BHK
- 1
- Total units
- 239
- Buildings
- 4
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 97% | 38% | 0% | 120 | |
| 97% | 38% | 0% | – | |
| 97% | 38% | 0% | – | |
| 97% | 38% | 0% | 120 |
"–" means MahaRERA shows no figure for that update.
About this project
Sea Breeze CHS Ltd by NDZ Infrastructure Private Limited is a 239-unit project in Chembur, Mumbai 400074, launched in August 2017; its MahaRERA registration has lapsed. 120 units booked out of total 239 units. The concrete structure (RCC) is 38% complete.
Read full summary
Sea Breeze CHS Ltd is a project by NDZ Infrastructure Private Limited in Chembur, Mumbai 400074, registered with MahaRERA as P51800008146. It was launched in August 2017. It has 239 units in 4 buildings, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2022. That date has passed and no extension has been recorded. Construction: excavation 97% complete, structure (RCC) 38% complete, final finishes not started.
120 units booked out of total 239 units (50%).