Arihant Residency, Sion
Ready to moveLapsed
by Arihant Infrastructure Company · Sion, Mumbai 400022 · Map
- Launched
- Aug 20172 yrs 1 mth originally promised
- Possession (MahaRERA)
- Mar 2026Extended by 6 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 45 of 10443%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 59
- 2 BHK
- 41
- Other units
- 4
- Total units
- 104
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 97% | 45 | |
| 100% | 100% | 97% | 45 | |
| 100% | 100% | 95% | 45 | |
| 100% | 100% | 95% | 102 |
"–" means MahaRERA shows no figure for that update.
About this project
Arihant Residency by Arihant Infrastructure Company is a 104-unit MHADA-sanctioned project in Sion, Mumbai 400022, launched in August 2017; its MahaRERA registration has lapsed. 45 units booked out of total 104 units. The concrete structure (RCC) is complete.
Read full summary
Arihant Residency is a MHADA-sanctioned project by Arihant Infrastructure Company in Sion, Mumbai 400022, registered with MahaRERA as P51800008281. It was launched in August 2017. It has 104 units in 1 building: 100 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2026, after an extension of 6 years 6 months from the original September 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
45 units booked out of total 104 units (43%).