Westend, Khar West

Lapsed

by Paramvir Builders LLP · Khar West, Mumbai 400052 · Map

Launched
Aug 20171 yr 10 mths promised
Possession (MahaRERA)
Jun 2019Not extendedWhat does Lapsed mean?
Concrete structure
80%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
5
3 BHK
6
Total units
11
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)80%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 20%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Excavation 95%Concrete structure (RCC) 80%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%80%20%–
95%80%20%–
95%80%20%11

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Westend by Paramvir Builders LLP is an 11-unit project in Khar West, Mumbai 400052, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 80% complete.

Read full summary

Westend is a project by Paramvir Builders LLP in Khar West, Mumbai 400052, registered with MahaRERA as P51800008462. It was launched in August 2017. It has 11 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2019. That date has passed and no extension has been recorded. Construction: excavation 95% complete, structure (RCC) 80% complete, final finishes 20% complete.