Senroofs, Mulund East

by Pioneer Housing · Mulund East, Mumbai 400081 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Weighted across 2 phases
Booked
–
Buildings
21.2 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
391
3 BHK
255
Total units
646
Buildings
2
Land
1.2 acres
Phases
2
MahaRERA complaints
4

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Senroofs Phase - II
Completed
P51800008478266100%–
Senroofs Phase - III
Nearing possession
P51800032087380100%97%
Show updates by phase

Senroofs Phase - II (P51800008478)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%–
100%100%10%–
100%100%10%195

"–" means MahaRERA shows no figure for that update.

Senroofs Phase - III (P51800032087)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%367
100%100%70%365
100%100%25%364
100%5%0%336

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services45%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 44%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 4%Dec 2025: Final finishes 19%Jul 2026: Final finishes 45%Oct 2026: Final finishes 45%Excavation 100%Concrete structure (RCC) 100%Final finishes 45%

How to read construction stages

Compared with 3 similar projects in PIN 400081

Projects with 300–1,300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400081
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths6 yrs 4 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)Dec 2027Dec 2024
Concrete structure (RCC)100%57%
MahaRERA complaints (filed by or against the builder)433

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Senroofs by Pioneer Housing is a 646-unit BMC-sanctioned project in Mulund East, Mumbai 400081, registered with MahaRERA in 2 phases, with possession due in December 2027. The concrete structure (RCC) is complete.

Read full summary

Senroofs is a BMC-sanctioned project by Pioneer Housing in Mulund East, Mumbai 400081, registered with MahaRERA as 2 phases (P51800008478, P51800032087). The first phase was launched in August 2017. Together the phases have 646 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 45% complete. Both phases have their structure complete.