Senroofs, Mulund East
by Pioneer Housing · Mulund East, Mumbai 400081 · Map
- Launched
- Aug 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- –
- Buildings
- 21.2 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 391
- 3 BHK
- 255
- Total units
- 646
- Buildings
- 2
- Land
- 1.2 acres
- Phases
- 2
- MahaRERA complaints
- 4
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Senroofs Phase - II Completed | P51800008478 | 266 | 100% | – | |
| Senroofs Phase - III Nearing possession | P51800032087 | 380 | 100% | 97% |
Show updates by phase
Senroofs Phase - II (P51800008478)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | 195 |
"–" means MahaRERA shows no figure for that update.
Senroofs Phase - III (P51800032087)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 367 | |
| 100% | 100% | 70% | 365 | |
| 100% | 100% | 25% | 364 | |
| 100% | 5% | 0% | 336 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 3 similar projects in PIN 400081
Projects with 300–1,300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 6 yrs 4 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2024 |
| Concrete structure (RCC) | 100% | 57% |
| MahaRERA complaints (filed by or against the builder) | 4 | 33 |
The 3 projects
- Aveza Phase 1, Mulund East
- Anutham, Mulund East
- Matoshree Nisarg Tower A, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aveza Phase 1 | August 2017 | December 2024 | 57% | 1 unit booked out of total 592 units |
| Anutham | August 2017 | June 2023 | 73% | 351 units booked out of total 471 units |
| Matoshree Nisarg Tower A | August 2017 | June 2025 | 55% | – |
About this project
Senroofs by Pioneer Housing is a 646-unit BMC-sanctioned project in Mulund East, Mumbai 400081, registered with MahaRERA in 2 phases, with possession due in December 2027. The concrete structure (RCC) is complete.
Read full summary
Senroofs is a BMC-sanctioned project by Pioneer Housing in Mulund East, Mumbai 400081, registered with MahaRERA as 2 phases (P51800008478, P51800032087). The first phase was launched in August 2017. Together the phases have 646 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.
The registered possession date is December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 45% complete. Both phases have their structure complete.