Matoshree Nisarg Tower A, Mulund East
Lapsed
by Matoshree Infrastructure Private Limited · Mulund East, Mumbai 400081 · Map
- Launched
- Aug 20177 yrs 10 mths promised
- Possession (MahaRERA)
- Jun 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 55%Mid-construction
- Booked
- –
- Buildings
- 11.4 acres
- MahaRERA complaints
- 43Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 4
- 2 BHK
- 200
- 3 BHK
- 81
- 4 BHK
- 27
- Total units
- 312
- Buildings
- 1
- Land
- 1.4 acres
- Phases
- 1
- MahaRERA complaints
- 43
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 55% | 0% | – | |
| 100% | 55% | 0% | – | |
| 100% | 55% | 0% | 292 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400081
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 10 mths | 3 yrs 8 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | Jun 2025 | Dec 2024 |
| Concrete structure (RCC) | 55% | 73% |
| MahaRERA complaints (filed by or against the builder) | 43 | 4 |
The 3 projects
- Anutham, Mulund East
- Aveza Phase 1, Mulund East
- Senroofs, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Anutham | August 2017 | June 2023 | 73% | 351 units booked out of total 471 units |
| Aveza Phase 1 | August 2017 | December 2024 | 57% | 1 unit booked out of total 592 units |
| Senroofs | August 2017 | Dec 2027 | 100% | – |
About this project
Matoshree Nisarg Tower A by Matoshree Infrastructure Private Limited is a 312-unit project in Mulund East, Mumbai 400081, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 55% complete.
Read full summary
Matoshree Nisarg Tower A is a project by Matoshree Infrastructure Private Limited in Mulund East, Mumbai 400081, registered with MahaRERA as P51800005541. It was launched in August 2017. It has 312 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 55% complete, final finishes not started.