Redevelopment of OB swarganga chsl CTS no 154 pt survey no 383 pt chaitanya ngr santacruz e mum 55, Bandra East
Lapsed
by A A Estates Pvt Ltd · Bandra East, Mumbai 400051 · Map
- Launched
- Aug 20171 yr 4 mths originally promised
- Possession (MahaRERA)
- Dec 2021Extended by 3 yrsWhat does Lapsed mean?
- Concrete structure
- 87%Mid-construction
- Booked
- 20 of 2483%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 23
- 3 BHK
- 1
- Total units
- 24
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 8% | 20 | |
| 100% | 87% | 8% | – | |
| 100% | 87% | 8% | – | |
| 100% | 87% | 8% | 20 |
"–" means MahaRERA shows no figure for that update.
About this project
Redevelopment of OB swarganga chsl CTS no 154 pt survey no 383 pt chaitanya ngr santacruz e mum 55 by A A Estates Pvt Ltd is a 24-unit project in Bandra East, Mumbai 400051, launched in August 2017; its MahaRERA registration has lapsed. 20 units booked out of total 24 units. The concrete structure (RCC) is 87% complete.
Read full summary
Redevelopment of OB swarganga chsl CTS no 154 pt survey no 383 pt chaitanya ngr santacruz e mum 55 is a project by A A Estates Pvt Ltd in Bandra East, Mumbai 400051, registered with MahaRERA as P51800008635. It was launched in August 2017. It has 24 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2021, after an extension of 3 years from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 87% complete, final finishes 8% complete.
20 units booked out of total 24 units (83%).