Jangid Annexe, Jogeshwari East

Lapsed

by Jangid Home pvt Ltd · Jogeshwari East, Mumbai 400060 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Jun 2024Extended by 5 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
25%Mid-construction
Booked
38 of 38100%
Buildings
10.4 acres
MahaRERA complaints
26Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
38
Total units
38
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)25%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 25%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 25%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 25%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%38
100%25%0%–
100%25%0%–
100%25%0%38

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Jangid Annexe by Jangid Home pvt Ltd is a 38-unit project in Jogeshwari East, Mumbai 400060, launched in August 2017; its MahaRERA registration has lapsed. 38 units booked out of total 38 units. The concrete structure (RCC) is 25% complete.

Read full summary

Jangid Annexe is a project by Jangid Home pvt Ltd in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800008642. It was launched in August 2017. It has 38 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2024, after an extension of 5 years 6 months from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.

38 units booked out of total 38 units (100%).