Siddharth Nagar Gulmohar Chs Ltd, Goregaon West
by Shivam Parivar Developers Pvt Ltd · Goregaon West, Mumbai 400104 · Map
- Launched
- Aug 20177 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 2 yrs
- Concrete structure
- 94%Mid-construction
- Booked (free sale)
- 131 of 131100% · 24 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale131 booked out of 131 units
Rehab24 units for existing members
Total 155 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 72
- 2 BHK
- 74
- Other units
- 9
- Total units
- 155
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 6
- Free-sale units
- 131
- Rehab units
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 94% | 53% | 131 | |
| 100% | 94% | 53% | 131 | |
| 100% | 94% | 53% | 131 | |
| 100% | 94% | 53% | 128 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400104
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 7 yrs 4 mths | 5 yrs 4 mths |
| Possession date extended | By 2 yrs | 2 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2025 |
| Concrete structure (RCC) | 94% | 78% |
| MahaRERA complaints (filed by or against the builder) | 6 | 1 |
The 3 projects
- Shatrunjay Plaza, Goregaon West
- Raj Pantheon, Goregaon West
- Kenorita Jewels, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shatrunjay Plaza | August 2017 | December 2024 | 78% | – |
| Raj Pantheon | August 2017 | December 2025 | 100% | 173 units booked out of total 180 units |
| Kenorita Jewels | September 2017 | Dec 2027 | 69% | – |
About this project
Siddharth Nagar Gulmohar Chs Ltd by Shivam Parivar Developers Pvt Ltd is a 155-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in August 2017 with possession due in December 2026. 131 units booked out of 131 units for sale. The concrete structure (RCC) is 94% complete.
Read full summary
Siddharth Nagar Gulmohar Chs Ltd is a MHADA-sanctioned project by Shivam Parivar Developers Pvt Ltd in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800008681. It was launched in August 2017. It has 155 units in 1 building: 146 homes (1 and 2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 155 units, 131 are for sale and 24 are rehab units for existing members.
Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) 94% complete, final finishes 53% complete.
131 units booked out of 131 units for sale (100%).