Raj Pantheon, Goregaon West

Lapsed

by Rajesh Arvind Surti · Goregaon West, Mumbai 400104 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 3 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
173 of 18096%
Buildings
10.5 acres
MahaRERA complaints
23Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
87
3 BHK
87
Other units
6
Total units
180
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
23
Reserved units
68

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 10%Dec 2025: Final finishes 50%Jul 2026: Final finishes 70%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%173
100%100%70%173
100%100%50%172
100%100%10%101

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400104

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400104
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths7 yrs 4 mths
Possession date extendedBy 3 yrs2 of 4
Possession date (MahaRERA)Dec 2025Dec 2026
Concrete structure (RCC)100%74%
MahaRERA complaints (filed by or against the builder)232

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Raj Pantheon by Rajesh Arvind Surti is a 180-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in August 2017; its MahaRERA registration has lapsed. 173 units booked out of total 180 units. The concrete structure (RCC) is complete.

Read full summary

Raj Pantheon is a MHADA-sanctioned project by Rajesh Arvind Surti in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800003673. It was launched in August 2017. It has 180 units in 1 building: 174 homes (1 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 3 years from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.

173 units booked out of total 180 units (96%).