Ariana Residency, Borivali East
Ready to moveLapsed
by J V Realty And Developers · Borivali East, Mumbai 400066 · Map
- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Jun 2022Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 30.5 acres
- MahaRERA complaints
- 25Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 333
- 2 BHK
- 2
- Total units
- 335
- Buildings
- 3
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 25
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 93% | – | |
| 100% | 100% | 93% | – | |
| 100% | 100% | 93% | 281 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400066
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 2 yrs 4 mths |
| Possession date extended | By 1 yr | 3 of 3 |
| Possession date (MahaRERA) | Jun 2022 | Dec 2025 |
| Concrete structure (RCC) | 100% | 89% |
| Units booked | – | 61% |
| MahaRERA complaints (filed by or against the builder) | 25 | 6 |
The 3 projects
- 4810 Heights, Borivali East
- Tatva, Borivali East
- Shashwat Residency, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| 4810 Heights | August 2017 | April 2028 | 89% | 126 units booked out of total 164 units |
| Tatva | August 2017 | December 2019 | 100% | 94 units booked out of total 155 units |
| Shashwat Residency | July 2017 | December 2025 | 6% | 69 units booked out of 193 units for sale |
About this project
Ariana Residency by J V Realty And Developers is a 335-unit project in Borivali East, Mumbai 400066, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Ariana Residency is a project by J V Realty And Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800008691. It was launched in August 2017. It has 335 units in 3 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2022, after an extension of 1 year from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 93% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.