Pashmina Lotus, Chandivali

Lapsed

by Pashmina Realty Private Limited · Chandivali, Mumbai 400072 · Map

Launched
Aug 20174 yrs 4 mths promised
Possession (MahaRERA)
Dec 2021Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
23 of 6734%
Buildings
30.3 acres
MahaRERA complaints
5Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
2
4 BHK
64
Total units
67
Buildings
3
Land
0.3 acres
Phases
1
MahaRERA complaints
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%23
0%0%0%–
0%0%0%–
0%0%0%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pashmina Lotus by Pashmina Realty Private Limited is a 67-unit project in Chandivali, Mumbai 400072, launched in August 2017; its MahaRERA registration has lapsed. 23 units booked out of total 67 units. Work on the concrete structure (RCC) has not started.

Read full summary

Pashmina Lotus is a project by Pashmina Realty Private Limited in Chandivali, Mumbai 400072, registered with MahaRERA as P51800008883. It was launched in August 2017. It has 67 units in 3 buildings, with 1 RK, 1 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2021. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.

23 units booked out of total 67 units (34%).