New Jagdamba, Andheri East
Lapsed
by SiroyaFM Constructions Pvt Ltd · Andheri East, Mumbai 400093 · Map
- Launched
- Aug 20172 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2021Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 95%Mid-construction
- Booked
- –
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 15
- Other units
- 2
- Total units
- 17
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 95% | 0% | – | |
| 95% | 95% | 0% | – | |
| 95% | 95% | 0% | 16 |
"–" means MahaRERA shows no figure for that update.
About this project
New Jagdamba by SiroyaFM Constructions Pvt Ltd is a 17-unit project in Andheri East, Mumbai 400093, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 95% complete.
Read full summary
New Jagdamba is a project by SiroyaFM Constructions Pvt Ltd in Andheri East, Mumbai 400093, registered with MahaRERA as P51800008985. It was launched in August 2017. It has 17 units in 1 building: 15 homes (2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2021, after an extension of 2 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 95% complete, final finishes not started.