Naik Kakad Niwas, Bandra West

Lapsed

by Niraj Kakad Constructions Private Limited · Bandra West, Mumbai 400050 · Map

Launched
Aug 20172 yrs 5 mths originally promised
Possession (MahaRERA)
Jan 2022Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
94%Mid-construction
Booked
3 of 2313%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
7
5+ BHK
1
Other units
15
Total units
23
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)94%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 94%Dec 2025: Concrete structure (RCC) 94%Jul 2026: Concrete structure (RCC) 94%Oct 2026: Concrete structure (RCC) 94%Dec 2024: Final finishes 30%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 94%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%94%30%3
100%94%30%–
100%94%30%–
100%94%30%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400050

Projects with up to 20 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths5 yrs 4 mths
Possession date extendedBy 2 yrs3 of 4
Possession date (MahaRERA)Jan 2022Sep 2024
Concrete structure (RCC)94%70%
Units booked13%57%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Naik Kakad Niwas by Niraj Kakad Constructions Private Limited is a 23-unit project in Bandra West, Mumbai 400050, launched in August 2017; its MahaRERA registration has lapsed. 3 units booked out of total 23 units. The concrete structure (RCC) is 94% complete.

Read full summary

Naik Kakad Niwas is a project by Niraj Kakad Constructions Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as P51800009134. It was launched in August 2017. It has 23 units in 1 building: 8 homes (4 and 5+ BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2022, after an extension of 2 years from the original January 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 94% complete, final finishes 30% complete.

3 units booked out of total 23 units (13%).