Naik Kakad Niwas, Bandra West
Lapsed
by Niraj Kakad Constructions Private Limited · Bandra West, Mumbai 400050 · Map
- Launched
- Aug 20172 yrs 5 mths originally promised
- Possession (MahaRERA)
- Jan 2022Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 94%Mid-construction
- Booked
- 3 of 2313%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 7
- 5+ BHK
- 1
- Other units
- 15
- Total units
- 23
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 94% | 30% | 3 | |
| 100% | 94% | 30% | – | |
| 100% | 94% | 30% | – | |
| 100% | 94% | 30% | 3 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400050
Projects with up to 20 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 5 yrs 4 mths |
| Possession date extended | By 2 yrs | 3 of 4 |
| Possession date (MahaRERA) | Jan 2022 | Sep 2024 |
| Concrete structure (RCC) | 94% | 70% |
| Units booked | 13% | 57% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Hiland Hub, Bandra West
- Crown, Bandra West
- Westside, Bandra West
- Pali Darshan Chs Ltd, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Hiland Hub | August 2017 | July 2023 | 40% | – |
| Crown | August 2017 | November 2025 | 20% | 4 units booked out of total 13 units |
| Westside | August 2017 | March 2028 | 100% | 18 units booked out of total 19 units |
| Pali Darshan Chs Ltd | July 2017 | June 2019 | 100% | 8 units booked out of total 14 units |
About this project
Naik Kakad Niwas by Niraj Kakad Constructions Private Limited is a 23-unit project in Bandra West, Mumbai 400050, launched in August 2017; its MahaRERA registration has lapsed. 3 units booked out of total 23 units. The concrete structure (RCC) is 94% complete.
Read full summary
Naik Kakad Niwas is a project by Niraj Kakad Constructions Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as P51800009134. It was launched in August 2017. It has 23 units in 1 building: 8 homes (4 and 5+ BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in January 2022, after an extension of 2 years from the original January 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 94% complete, final finishes 30% complete.
3 units booked out of total 23 units (13%).