Skip to main content

Hersh Aangan By Tridhaatu, Chembur

Lapsed

by Tridhaatu Bharadwaj Developers LLP · Chembur, Mumbai 400074 · Map

Launched
Aug 20176 yrs 4 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
8 of 7810%
Buildings
20.7 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
37
3 BHK
39
Other units
2
Total units
78
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%8
50%0%0%–
50%0%0%–
50%0%0%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Hersh Aangan By Tridhaatu by Tridhaatu Bharadwaj Developers LLP is a 78-unit project in Chembur, Mumbai 400074, launched in August 2017; its MahaRERA registration has lapsed. 8 units booked out of total 78 units. Work on the concrete structure (RCC) has not started.

Read full summary

Hersh Aangan By Tridhaatu is a project by Tridhaatu Bharadwaj Developers LLP in Chembur, Mumbai 400074, registered with MahaRERA as P51800009256. It was launched in August 2017. It has 78 units in 2 buildings: 76 homes (2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.

8 units booked out of total 78 units (10%).

Tridhaatu's track record in Mumbai

MahaRERA projects registered 2017–2023 in Mumbai

Projects registered with MahaRERA12
Total units across these projects649
Completed without extending the possession date1
Completed after an extension1
Lapsed6
Under construction4
Possession date extended on the builder's application6
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Tridhaatu projects33 (10 of 12 projects)

See all Tridhaatu projects →