Whispering Tower-Abcd, Mulund West

Lapsed

by Housing Development And Infrastructure Ltd · Mulund West, Mumbai 400080 · Map

Launched
Aug 20175 yrs 2 mths promised
Possession (MahaRERA)
Oct 2022Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
92 of 75412%
Buildings
82.7 acres
MahaRERA complaints
11Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
754
Total units
754
Buildings
8
Land
2.7 acres
Phases
1
MahaRERA complaints
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation32%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 32%Dec 2025: Excavation 32%Jul 2026: Excavation 32%Oct 2026: Excavation 32%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 32%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
32%0%0%92
32%0%0%–
32%0%0%–
32%0%0%92

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Whispering Tower-Abcd by Housing Development And Infrastructure Ltd is a 754-unit project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 92 units booked out of total 754 units. Work on the concrete structure (RCC) has not started.

Read full summary

Whispering Tower-Abcd is a project by Housing Development And Infrastructure Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800009742. It was launched in August 2017. It has 754 units in 8 buildings, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2022. That date has passed and no extension has been recorded. Construction: excavation 32% complete, structure (RCC) not started, final finishes not started.

92 units booked out of total 754 units (12%).