Chintamani Glory, Ghatkopar West

Lapsed

by Chintamani Realty · Ghatkopar West, Mumbai 400084 · Map

Launched
Aug 20171 yr 7 mths originally promised
Possession (MahaRERA)
Dec 2021Extended by 2 yrs 9 mthsWhat does Lapsed mean?
Concrete structure
8%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
45
Total units
45
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)8%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 8%Dec 2025: Concrete structure (RCC) 8%Jul 2026: Concrete structure (RCC) 8%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Final finishes 50%Concrete structure (RCC) 8%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%8%50%–
100%8%50%–
100%8%50%45

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Chintamani Glory by Chintamani Realty is a 45-unit SRA-sanctioned project in Ghatkopar West, Mumbai 400084, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 8% complete.

Read full summary

Chintamani Glory is an SRA-sanctioned project by Chintamani Realty in Ghatkopar West, Mumbai 400084, registered with MahaRERA as P51800009774. It was launched in August 2017. It has 45 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2021, after an extension of 2 years 9 months from the original March 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 8% complete, final finishes 50% complete.