Ariisto Sommet-Residential, Goregaon West

Lapsed

by Ashvi Developers Private Limited · Goregaon West, Mumbai 400090 · Map

Launched
Aug 20176 yrs 4 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
15%Mid-construction
Booked
115 of 22052%
Buildings
12.7 acres
MahaRERA complaints
19Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
144
4 BHK
72
Other units
4
Total units
220
Buildings
1
Land
2.7 acres
Phases
1
MahaRERA complaints
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)15%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 15%Dec 2025: Concrete structure (RCC) 15%Jul 2026: Concrete structure (RCC) 15%Oct 2026: Concrete structure (RCC) 15%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 15%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%0%115
100%15%0%–
100%15%0%–
100%15%0%115

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ariisto Sommet-Residential by Ashvi Developers Private Limited is a 220-unit project in Goregaon West, Mumbai 400090, launched in August 2017; its MahaRERA registration has lapsed. 115 units booked out of total 220 units. The concrete structure (RCC) is 15% complete.

Read full summary

Ariisto Sommet-Residential is a project by Ashvi Developers Private Limited in Goregaon West, Mumbai 400090, registered with MahaRERA as P51800009848. It was launched in August 2017. It has 220 units in 1 building: 216 homes (3 and 4 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started.

115 units booked out of total 220 units (52%).