Skip to main content

Nishchay, Dahisar

Lapsed

by Shreeraj Developer LLP · Dahisar, Mumbai 400068 · Map

Launched
Aug 2017First of 5 phases
Possession (MahaRERA)
Dec 2024 – Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Weighted across 5 phases
Booked
–
Buildings
50.2 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
899
2 BHK
266
Total units
1,165
Buildings
5
Land
0.2 acres
Phases
5
MahaRERA complaints
6

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Nishchay Wing F
Completed
P51800009954167100%–
Nishchay - Wing E
Completed
P51800015985167100%–
Nishchay Wing D
Nearing possession Lapsed
P51800016172167100%–
Nishchay Wing A
Ready to move Lapsed
P51800019863198100%–
NISHCHAY Wing B
Completed
P51800019891466100%–
Show updates by phase

Nishchay Wing F (P51800009954)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%55%–
100%100%55%–
100%100%55%163

"–" means MahaRERA shows no figure for that update.

Nishchay - Wing E (P51800015985)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%55%–
100%100%55%–
100%100%55%166

"–" means MahaRERA shows no figure for that update.

Nishchay Wing D (P51800016172)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%15%–
100%100%15%–
100%100%15%166

"–" means MahaRERA shows no figure for that update.

Nishchay Wing A (P51800019863)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%92%–
100%100%92%–
100%100%92%198

"–" means MahaRERA shows no figure for that update.

NISHCHAY Wing B (P51800019891)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%92%–
100%100%92%–
100%100%92%463

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 70%Dec 2025: Final finishes 70%Jul 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

How to read construction stages

About this project

Nishchay by Shreeraj Developer LLP is a 1,165-unit project in Dahisar, Mumbai 400068, registered with MahaRERA in 5 phases, with possession dates from December 2024 to December 2025. The concrete structure (RCC) is complete.

Read full summary

Nishchay is a project by Shreeraj Developer LLP in Dahisar, Mumbai 400068, registered with MahaRERA as 5 phases (P51800009954, P51800015985, P51800016172, P51800019863, P51800019891). The first phase was launched in August 2017. Together the phases have 1,165 units in 5 buildings, with 1 and 2 BHK homes as registered with MahaRERA. On MahaRERA, 3 are completed and 2 are lapsed.

The phases' registered possession dates run from December 2024 to December 2025; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 70% complete. All 5 phases have their structure complete.