- Launched
- Aug 2017First of 5 phases
- Possession (MahaRERA)
- Dec 2024 – Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Weighted across 5 phases
- Booked
- –
- Buildings
- 50.2 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 899
- 2 BHK
- 266
- Total units
- 1,165
- Buildings
- 5
- Land
- 0.2 acres
- Phases
- 5
- MahaRERA complaints
- 6
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Nishchay Wing F Completed | P51800009954 | 167 | 100% | – | |
| Nishchay - Wing E Completed | P51800015985 | 167 | 100% | – | |
| Nishchay Wing D Nearing possession Lapsed | P51800016172 | 167 | 100% | – | |
| Nishchay Wing A Ready to move Lapsed | P51800019863 | 198 | 100% | – | |
| NISHCHAY Wing B Completed | P51800019891 | 466 | 100% | – |
Show updates by phase
Nishchay Wing F (P51800009954)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 55% | – | |
| 100% | 100% | 55% | – | |
| 100% | 100% | 55% | 163 |
"–" means MahaRERA shows no figure for that update.
Nishchay - Wing E (P51800015985)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 55% | – | |
| 100% | 100% | 55% | – | |
| 100% | 100% | 55% | 166 |
"–" means MahaRERA shows no figure for that update.
Nishchay Wing D (P51800016172)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 15% | – | |
| 100% | 100% | 15% | – | |
| 100% | 100% | 15% | 166 |
"–" means MahaRERA shows no figure for that update.
Nishchay Wing A (P51800019863)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 92% | – | |
| 100% | 100% | 92% | – | |
| 100% | 100% | 92% | 198 |
"–" means MahaRERA shows no figure for that update.
NISHCHAY Wing B (P51800019891)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 92% | – | |
| 100% | 100% | 92% | – | |
| 100% | 100% | 92% | 463 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Nishchay by Shreeraj Developer LLP is a 1,165-unit project in Dahisar, Mumbai 400068, registered with MahaRERA in 5 phases, with possession dates from December 2024 to December 2025. The concrete structure (RCC) is complete.
Read full summary
Nishchay is a project by Shreeraj Developer LLP in Dahisar, Mumbai 400068, registered with MahaRERA as 5 phases (P51800009954, P51800015985, P51800016172, P51800019863, P51800019891). The first phase was launched in August 2017. Together the phases have 1,165 units in 5 buildings, with 1 and 2 BHK homes as registered with MahaRERA. On MahaRERA, 3 are completed and 2 are lapsed.
The phases' registered possession dates run from December 2024 to December 2025; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 70% complete. All 5 phases have their structure complete.