Siddharth Nagar Abhiman Chs Ltd Building No-25, Goregaon West

Lapsed

by Mumbai Shelter Housing Development Pvt Ltd · Goregaon West, Mumbai 400062 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
72%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
1
2 BHK
48
Total units
50
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)72%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 72%Dec 2025: Concrete structure (RCC) 72%Jul 2026: Concrete structure (RCC) 72%Dec 2024: Final finishes 70%Dec 2025: Final finishes 70%Jul 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 72%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%70%–
100%72%70%–
100%72%70%37

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Siddharth Nagar Abhiman Chs Ltd Building No-25 by Mumbai Shelter Housing Development Pvt Ltd is a 50-unit project in Goregaon West, Mumbai 400062, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 72% complete.

Read full summary

Siddharth Nagar Abhiman Chs Ltd Building No-25 is a project by Mumbai Shelter Housing Development Pvt Ltd in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800010246. It was launched in August 2017. It has 50 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 72% complete, final finishes 70% complete.